Site navigation

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same work in 2 days, then what is the time taken by 15 men and 20 boys to complete the same type of work?

Question and options

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same work in 2 days, then what is the time taken by 15 men and 20 boys to complete the same type of work?
  1. 4 days
  2. 5 days
  3. 6 days
  4. 7 days

Answer and explanation

Correct answer: A - 4 days
Let one man do mm and one boy bb per day: 6m+8b=1106m + 8b = \frac{1}{10} and 26m+48b=1226m + 48b = \frac{1}{2}. Multiplying the first by 6 gives 36m+48b=0.636m + 48b = 0.6; subtracting, 10m=0.110m = 0.1, m=0.01m = 0.01, then b=0.005b = 0.005. 15m+20b=0.15+0.10=0.2515m + 20b = 0.15 + 0.10 = 0.25 per day, so 4 days.