A is \(40 \%\) less efficient than \(B\) who can do the same work in \(20 \%\) less time than \(C\). If \(A\) and B together can complete \(80 \%\) work in 12 days, then in how many days \(60 \%\)…
Question and options
A is less efficient than who can do the same work in less time than . If and B together can complete work in 12 days, then in how many days work can be completed by and together ?
- 2 days
- 4 days
- 8 days
- 16 days
Answer and explanation
Correct answer: C - 8 days
A and B do 80% in 12 days, so 100% in 15 days. A = 0.6B, so 1.6B = 1/15 and B = 1/24 per day. C takes 24/0.8 = 30 days, so C = 1/30. B+C = 1/24 + 1/30 = 3/40 per day. 60% of the work takes 0.6 x 40/3 = 8 days.
Practice for these exams
-
JIPMAT
Related question papers
Related exam syllabi
More solved explanations in Arithmetic
- The average salary per month of 30 employees in a company is ₹ 4,000. If the Manager’s salary is added, the average salary increases to ₹ 4,300, what is the salary…
- How many degrees are there between clock hands at 3.15 ?
- On dividing each of 187, 233 and 279 by 'x', the same remainder is obtained in each case. Maximum value of such number 'x' is -
- A motorist travels to place 150 km away at an average speed of 50 km/hr and returns at 30 km/hr. Find out the average speed for whole journey.
- Assume each cat catches mice at the same constant rate. If 100 cats catch 100 mice in 100 minutes, how long will 7 cats take to catch 7 mice?