Which of these activities is not one of the activities recommended to be performed by an independent SQA group?

Select one answer
Answer and explanation

Correct answer D

An independent Software Quality Assurance (SQA) group prepares the SQA plan, audits software engineering activities for process compliance, and reports non-compliance, but does NOT serve as the sole test team for the software.