Boehm's COCOMO II hierarchy consists of three estimation submodels corresponding to successive stages of software development: the Application composition model, the Early…
Choose your answer
Which of the following is NOT one of the submodels in the COCOMO II (COnstructive COst Model II) hierarchy of estimation models?
Answer and explanation
Correct answer C
Boehm's COCOMO II hierarchy consists of three estimation submodels corresponding to successive stages of software development: the Application composition model, the Early design stage model, and the Post-architecture-stage model. "Maintenance model" is not a submodel in the COCOMO II hierarchy.