Site navigation

Which of the following is NOT one of the submodels in the COCOMO II (COnstructive COst Model II)…

Boehm's COCOMO II hierarchy consists of three estimation submodels corresponding to successive stages of software development: the Application composition model, the Early…

Choose your answer

Which of the following is NOT one of the submodels in the COCOMO II (COnstructive COst Model II) hierarchy of estimation models?

Select one answer
Answer and explanation

Correct answer C

Boehm's COCOMO II hierarchy consists of three estimation submodels corresponding to successive stages of software development: the Application composition model, the Early design stage model, and the Post-architecture-stage model. "Maintenance model" is not a submodel in the COCOMO II hierarchy.

Practice for these exams

  • Rajasthan Analyst Cum Programmer

Related question papers

Related questions in this topic