Which of the following is not one of the guiding principles of software project scheduling

The guiding principles of software project scheduling include Compartmentalization, Interdependency, Time allocation, Effort validation, Defined responsibilities, Defined…

Choose your answer

Which of the following is not one of the guiding principles of software project scheduling

Select one answer
Answer and explanation

Correct answer B

The guiding principles of software project scheduling include Compartmentalization, Interdependency, Time allocation, Effort validation, Defined responsibilities, Defined outcomes, and Defined milestones; 'Market assessment' is not a scheduling principle.