Which of the following is NOT a sub-model of the COCOMO-II model?
Barry Boehm's COCOMO-II software cost estimation model consists of three stage-based sub-models: the Application Composition (early prototyping) model, the Early Design…
Choose your answer
Which of the following is NOT a sub-model of the COCOMO-II model?
Answer and explanation
Correct answer C
Barry Boehm's COCOMO-II software cost estimation model consists of three stage-based sub-models: the Application Composition (early prototyping) model, the Early Design model, and the Post-Architecture model. 'The early testing model' is not a COCOMO-II sub-model.