Which of the following is NOT a sub-model of the COCOMO-II model?

Barry Boehm's COCOMO-II software cost estimation model consists of three stage-based sub-models: the Application Composition (early prototyping) model, the Early Design…

Choose your answer

Which of the following is NOT a sub-model of the COCOMO-II model?

Select one answer
Answer and explanation

Correct answer C

Barry Boehm's COCOMO-II software cost estimation model consists of three stage-based sub-models: the Application Composition (early prototyping) model, the Early Design model, and the Post-Architecture model. 'The early testing model' is not a COCOMO-II sub-model.