The time delays of the four segments in the pipeline are as follows : t1 = 50 ns, t2 = 30 ns, t3 = 95…

The total time is 10300 ns. The pipeline clock period is the longest segment delay plus the interface delay, \(95+5=100\) ns. Four stages and 100 tasks require…

Choose your answer

The time delays of the four segments in the pipeline are as follows : t1 = 50 ns, t2 = 30 ns, t3 = 95 ns and t4 = 45 ns. The interface delay time tr = 5 ns. How long will it take to complete 100 tasks in the pipeline ?

Select one answer
Answer and explanation

Correct answer B

The total time is 10300 ns. The pipeline clock period is the longest segment delay plus the interface delay, 95+5=10095+5=100 ns. Four stages and 100 tasks require 4+100−1=1034+100-1=103 cycles, giving 103×100=10300103\times100=10300 ns.