Match the items of List – I with List – II : List – I List – II a. PERT i. Strategies b. CPM ii. Events…

Program Evaluation and Review Technique (PERT) is probabilistic and event-oriented (ii), Critical Path Method (CPM) is a deterministic activity-on-network scheduling…

Choose your answer

Match the items of List – I with List – II :

List – I

List – II a. PERT i. Strategies b. CPM ii. Events c. Game theory

iii. Network

Codes : a b c

Select one answer
Answer and explanation

Correct answer B

Program Evaluation and Review Technique (PERT) is probabilistic and event-oriented (ii), Critical Path Method (CPM) is a deterministic activity-on-network scheduling technique (iii), and Game Theory analyzes competitive decision-making using players' strategies and payoff matrices (i).