Match the items of List – I with List – II : List – I List – II a. PERT i. Strategies b. CPM ii. Events…
Program Evaluation and Review Technique (PERT) is probabilistic and event-oriented (ii), Critical Path Method (CPM) is a deterministic activity-on-network scheduling…
Choose your answer
Match the items of List – I with List – II :
List – I
List – II a. PERT i. Strategies b. CPM ii. Events c. Game theory
iii. Network
Codes : a b c
Answer and explanation
Correct answer B
Program Evaluation and Review Technique (PERT) is probabilistic and event-oriented (ii), Critical Path Method (CPM) is a deterministic activity-on-network scheduling technique (iii), and Game Theory analyzes competitive decision-making using players' strategies and payoff matrices (i).