Estimate factory cost of the product if direct material is Rs.60,000; Direct Labour is Rs.40,000 and…

Factory cost includes direct material, direct labour and factory overhead. Factory overhead is 40% of Rs.60,000 = Rs.24,000, so factory cost is Rs.60,000 + Rs.40,000 +…

Choose your answer

Estimate factory cost of the product if direct material is Rs.60,000; Direct Labour is Rs.40,000 and factory overhead 40% of the direct material:

Select one answer
Answer and explanation

Correct answer A

Factory cost includes direct material, direct labour and factory overhead. Factory overhead is 40% of Rs.60,000 = Rs.24,000, so factory cost is Rs.60,000 + Rs.40,000 + Rs.24,000 = Rs.1,24,000.