Site navigation

Assume B is social benefits, C is social costs, r is the social discount rate, t is the time and T is…

NPV=Σ(Bt−Ct)/(1+r)^t. Reversing net benefits flips sign, inverting the fraction changes its economic units, and usingCt^t ignores discounting. Only discounted benefits minus…

Choose your answer

Assume B is social benefits, C is social costs, r is the social discount rate, t is the time and T is the life of the investment project. The Net Present Value (NPV) of a project is

Select one answer
Answer and explanation

Correct answer A

NPV=Σ(Bt−Ct)/(1+r)^t. Reversing net benefits flips sign, inverting the fraction changes its economic units, and usingCt^t ignores discounting. Only discounted benefits minus costs is correct.