A, B and C work in a workshop for creating identical idols. A can craft 10 idols in 150 days. Similarly, B and C can individually create 16 idols in 192 days and 320 days, respectively. B works…
Question and options
A, B and C work in a workshop for creating identical idols. A can craft 10 idols in 150 days. Similarly, B and C can individually create 16 idols in 192 days and 320 days, respectively. B works every day, A works only on alternate days starting from the first day, i.e. 1st March, and C also works only on alternate days starting from the second day, i.e 2nd March. On which date will the construction of 2 idols be completed?
- 16 March
- 15 March
- 14 March
- 13 March
Answer and explanation
Correct answer: B - 15 March
Rates per day: A 1/15, B 1/12, C 1/20. Each 2-day block: 1/15 + 2/12 + 1/20 = 17/60. After 7 blocks (14 days, to 14 March) work = 119/60; need 1/60 more, done on day 15 (A+B work) = 15 March.
Practice for these exams
-
IIM Bangalore BBA DBE Entrance Test
Related question papers
Related exam syllabi
More solved explanations in Arithmetic
- The sum of the ages of son and father is 56 years. After four years, the age of the father will be three times that of the son. Their ages respectively are:
- A certain principal becomes 3 times itself in 12 years at a certain rate of compound interest. In how many years will it become 9 times itself?
- The ratio of income of two persons A and B is 8 : 5 and ratio of their expenditure is 5 : 3. If the savings of A and B are ₹ 2,400 and ₹ 2,000 respectively, then…
- A tradesman allows a discount of 15% on the marked price. How much above the cost price must he mark his goods to gain 19%?
- If \(5^{a} = 9^{b} = 2025\), then the value of \(\frac{ab}{a + b}\) is: