A, B and C work in a workshop for creating identical idols. A can craft 10 idols in 150 days. Similarly, B and C can individually create 16 idols in 192 days and 320 days, respectively. B works…

Question and options

A, B and C work in a workshop for creating identical idols. A can craft 10 idols in 150 days. Similarly, B and C can individually create 16 idols in 192 days and 320 days, respectively. B works every day, A works only on alternate days starting from the first day, i.e. 1st March, and C also works only on alternate days starting from the second day, i.e 2nd March. On which date will the construction of 2 idols be completed?
  1. 16 March
  2. 15 March
  3. 14 March
  4. 13 March

Answer and explanation

Correct answer: B - 15 March
Rates per day: A 1/15, B 1/12, C 1/20. Each 2-day block: 1/15 + 2/12 + 1/20 = 17/60. After 7 blocks (14 days, to 14 March) work = 119/60; need 1/60 more, done on day 15 (A+B work) = 15 March.

Practice for these exams

  • IIM Bangalore BBA DBE Entrance Test

Related question papers

Related exam syllabi

More solved explanations in Arithmetic