4 men and 5 women do a piece of work in 8 days while 7 men and 5 women finish it in 5 days. 3 men and 5 women will finish it in how many days?

Question and options

4 men and 5 women do a piece of work in 8 days while 7 men and 5 women finish it in 5 days. 3 men and 5 women will finish it in how many days?
  1. 8 days
  2. 10 days
  3. 12 days
  4. 15 days

Answer and explanation

Correct answer: B - 10 days
Let m, w be daily rates. 4m + 5w = 1/8 and 7m + 5w = 1/5, so 3m = 1/5 - 1/8 = 3/40, m = 1/40, and 5w = 1/8 - 4/40 = 1/40. Then 3m + 5w = 3/40 + 1/40 = 1/10, so 3 men and 5 women finish in 10 days.