20 men take 30 days to complete a piece of work. How many men are required to complete the work in 10 days?

Question and options

20 men take 30 days to complete a piece of work. How many men are required to complete the work in 10 days?
  1. 45
  2. 55
  3. 60
  4. 65

Answer and explanation

Correct answer: C - 60
Work = 20 x 30 = 600 man-days. To finish in 10 days you need 600 / 10 = 60 men.