Which section of the Indian Contract Act, 1872 governs the doctrine of frustration of contract?
Under the second paragraph of section 56, a contract becomes void when performance becomes impossible after formation, or unlawful because of an event the promisor could not…
Choose your answer
Which section of the Indian Contract Act, 1872 governs the doctrine of frustration of contract?
Answer and explanation
Correct answer A
Under the second paragraph of section 56, a contract becomes void when performance becomes impossible after formation, or unlawful because of an event the promisor could not prevent. The first paragraph deals with agreements to do acts that are impossible from the outset. Satyabrata Ghose v. Mugneeram Bangur & Co. (AIR 1954 SC 44) discusses frustration under section 56.
Option feedback
Option A
The second paragraph of section 56 governs supervening impossibility or unlawfulness.
Option B
Section 33 governs enforcement of a contingent contract that depends on an event not happening.
Option C
Section 75 gives a rightful rescinder a claim for loss caused by non-fulfilment.
Option D
Section 55 concerns failure to perform at a fixed time and whether time was essential.
Practice for these exams
-
All India Bar Examination (AIBE)
Subject revision
See pack details on LawMint.net -
UGC NET Law
Subject revision
See pack details on LawMint.net -
IIT Kharagpur LL.M. Entrance
Subject revision
See pack details on LawMint.net -
Assam Judicial Services
-
CLAT PG
Subject revision for a passage-based exam
-
CUET PG Law (LL.M.)
Subject revision
-
AILET PG
Subject revision
-
Supreme Court Law Clerk and Research Associate
Subject revision
-
Bihar Judicial Services
Subject revision
-
Uttarakhand Judicial Services
Subject revision