Which of the following is an actual breach of contract, as opposed to an anticipatory breach or a discharge without breach?

Question and options

Which of the following is an actual breach of contract, as opposed to an anticipatory breach or a discharge without breach?

  1. Before the date of a booked concert, the hall burns down without either party's fault

  2. Before the delivery date, a seller sells the contracted specific goods to someone else

  3. A seller fails to deliver the goods on the agreed delivery date

  4. A seller tells the buyer a week before the delivery date that it will not deliver

Answer and explanation

Correct answer: C - A seller fails to deliver the goods on the agreed delivery date

An actual breach occurs when a party fails to perform its promise when performance falls due, or performs defectively. Refusing in advance, or disabling oneself before the due date by selling the specific goods to another, is anticipatory breach, which section 39 of the Indian Contract Act, 1872 lets the promisee treat as ending the contract. Destruction of the hall without fault makes performance impossible, so the contract becomes void under section 56 rather than being broken.

Practice for these exams

  • All India Bar Examination (AIBE)

    Subject revision

  • IIT Kharagpur LL.M. Entrance

    Subject revision

  • UGC NET Law

    Subject revision

  • CLAT PG

    Subject revision for a passage-based exam

  • CUET PG Law (LL.M.)

    Subject revision

  • AILET PG

    Subject revision

  • Supreme Court Law Clerk and Research Associate

    Subject revision

  • Bihar Judicial Services

    Subject revision

  • Uttarakhand Judicial Services

    Subject revision

Related exam syllabi

More solved explanations in Discharge, impossibility & frustration