Which event is a preventive court remedy rather than a way of discharging contractual obligations?
A temporary injunction is preventive relief under sections 36 and 37 of the Specific Relief Act, 1963. Complete performance, valid substitution and termination following…
Choose your answer
Which event is a preventive court remedy rather than a way of discharging contractual obligations?
Answer and explanation
Correct answer D
A temporary injunction is preventive relief under sections 36 and 37 of the Specific Relief Act, 1963. Complete performance, valid substitution and termination following repudiation can discharge obligations under the Indian Contract Act, 1872.
Option feedback
Option A
Performing the promised obligations satisfies them.
Option B
When the parties validly substitute a new contract, section 62 releases them from performing the original one.
Option C
Section 39 allows the promisee to end the contract after repudiation of the whole promise, unless the promisee has accepted its continuance.
Option D
A temporary injunction provides preventive relief. The order itself does not discharge contractual obligations.
Practice for these exams
-
All India Bar Examination (AIBE)
Subject revision
See pack details on LawMint.net -
UGC NET Law
Subject revision
See pack details on LawMint.net -
IIT Kharagpur LL.M. Entrance
Subject revision
See pack details on LawMint.net -
West Bengal Judicial Services
-
CLAT PG
Subject revision for a passage-based exam
-
CUET PG Law (LL.M.)
Subject revision
-
AILET PG
Subject revision
-
Supreme Court Law Clerk and Research Associate
Subject revision
-
Bihar Judicial Services
Subject revision
-
Uttarakhand Judicial Services
Subject revision