When is a breach of contract described as anticipatory?
Question and options
When is a breach of contract described as anticipatory?
When a party fails to perform on the date fixed for performance
When performance becomes impossible after the contract is made
When a party performs late, after the date fixed for performance
When a party repudiates before the time for performance arrives
Answer and explanation
An anticipatory breach occurs when a party, before performance is due, refuses to perform his promise in its entirety or disables himself from performing it; under section 39 of the Indian Contract Act, 1872 the promisee may then end the contract unless he has signified acquiescence in its continuance. Failure to perform on the due date is an actual breach, and supervening impossibility is frustration under section 56, not breach.
Practice for these exams
-
All India Bar Examination (AIBE)
Subject revision
-
IIT Kharagpur LL.M. Entrance
Subject revision
-
UGC NET Law
Subject revision
-
CLAT PG
Subject revision for a passage-based exam
-
CUET PG Law (LL.M.)
Subject revision
-
AILET PG
Subject revision
-
Supreme Court Law Clerk and Research Associate
Subject revision
-
Bihar Judicial Services
Subject revision
-
Uttarakhand Judicial Services
Subject revision
Related exam syllabi
More solved explanations in Remedies for breach & damages
- Match List I with List II and select the correct answer using the codes below. Codes follow the order (a), (b), (c), (d). List IList II (a) Fazaluddin v. Panchu…
- Section 73 of the Indian Contract Act incorporates rules from which of the following cases ?
- The case Frost v. Knight (1872) LR 7 Ex. 111 related to:
- X contracts to supply Y with 1,000 tons of iron at Rs 100 a ton by a stated date. X then contracts to buy 1,000 tons of iron from A at Rs 80 a ton, telling A that…
- A stipulation for increased interest from the date of default is known as