Under the rule applied by the Court of Appeal of England and Wales in Williams v. Roffey Bros. (1989),…
Williams v. Roffey Bros. held that a practical benefit from securing performance of an existing duty can amount to consideration for a promise of additional payment.…
Choose your answer
Under the rule applied by the Court of Appeal of England and Wales in Williams v. Roffey Bros. (1989), a building contractor voluntarily promises a carpenter extra pay to finish agreed work on time. The contractor gains the practical benefit of reducing the risk of delay liability, and there is no fraud or economic duress. What follows as to consideration for the promise?
Answer and explanation
Correct answer B
Williams v. Roffey Bros. held that a practical benefit from securing performance of an existing duty can amount to consideration for a promise of additional payment.
Avoiding the risk of delay liability was such a benefit, and the rule assumes that the promise was not procured by fraud or economic duress.
Option feedback
Option A
An existing duty does not categorically prevent a practical benefit from providing consideration in this setting.
Option B
The prospect of avoiding delay liability is the kind of practical benefit the court accepted.
Option C
The inquiry concerns consideration for the later promise and does not turn on the object of the original bargain.
Option D
The case accepted that performance of the agreed work could yield sufficient practical benefit.
Practice for these exams
-
All India Bar Examination (AIBE)
Subject revision
See pack details on LawMint.net -
UGC NET Law
Subject revision
See pack details on LawMint.net -
IIT Kharagpur LL.M. Entrance
Subject revision
See pack details on LawMint.net -
Tamil Nadu Judicial Services
-
CLAT PG
Subject revision for a passage-based exam
-
CUET PG Law (LL.M.)
Subject revision
-
AILET PG
Subject revision
-
Supreme Court Law Clerk and Research Associate
Subject revision
-
Bihar Judicial Services
Subject revision
-
Uttarakhand Judicial Services
Subject revision