The principle of 'anticipatory breach of contract' has been given under which Section of the Indian…

Anticipatory breach, where a party refuses to perform or disables himself from performing his promise in its entirety, is governed by "Section 39" of the Indian Contract Act.

Choose your answer

The principle of 'anticipatory breach of contract' has been given under which Section of the Indian Contract Act, 1872?

Select one answer
Answer and explanation

Correct answer D

Anticipatory breach, where a party refuses to perform or disables himself from performing his promise in its entirety, is governed by "Section 39" of the Indian Contract Act.