An absolute refusal before the promised performance date is an anticipatory breach. Section 39 allows the promisee to put an end to the contract when the promisor refuses or…
Choose your answer
In the context of the Indian Contract Act, 1872, if a promisor absolutely repudiates the contract before the promised date of performance, it is:
Answer and explanation
Correct answer D
An absolute refusal before the promised performance date is an anticipatory breach. Section 39 allows the promisee to put an end to the contract when the promisor refuses or disables himself from performing the promise in its entirety, unless the promisee has signified acquiescence in continuation. It differs from frustration or impossibility occurring independently of such repudiation.
Practice for these exams
-
All India Bar Examination (AIBE)
Subject revision
See pack details on LawMint.net -
UGC NET Law
Subject revision
See pack details on LawMint.net -
IIT Kharagpur LL.M. Entrance
Subject revision
See pack details on LawMint.net -
Odisha Judicial Services
-
CLAT PG
Subject revision for a passage-based exam
-
CUET PG Law (LL.M.)
Subject revision
-
AILET PG
Subject revision
-
Supreme Court Law Clerk and Research Associate
Subject revision
-
Bihar Judicial Services
Subject revision
-
Uttarakhand Judicial Services
Subject revision