A valid contract requires a named expert to perform a service personally on a fixed date. Before that date, an unforeseen illness, for which the expert is not at fault, permanently leaves the expert…

Question and options

A valid contract requires a named expert to perform a service personally on a fixed date. Before that date, an unforeseen illness, for which the expert is not at fault, permanently leaves the expert unable to perform. What follows under section 56 of the Indian Contract Act, 1872?

  1. The contract remains valid, and the expert must pay damages

  2. The contract becomes voidable at the other party's option

  3. The contract is void from the start as an agreement to do an impossible act

  4. The contract becomes void when performance becomes impossible

Answer and explanation

Correct answer: D - The contract becomes void when performance becomes impossible

The second paragraph of section 56 makes a contract to do an act void when, after it is made, the act becomes impossible through an event the promisor could not prevent. It is not void from the start, since the act was possible when the contract was made; that rule, in the first paragraph, applies only to an act impossible in itself.

Practice for these exams

  • All India Bar Examination (AIBE)

    Subject revision

  • IIT Kharagpur LL.M. Entrance

    Subject revision

  • UGC NET Law

    Subject revision

  • CLAT PG

    Subject revision for a passage-based exam

  • CUET PG Law (LL.M.)

    Subject revision

  • AILET PG

    Subject revision

  • Supreme Court Law Clerk and Research Associate

    Subject revision

  • Bihar Judicial Services

    Subject revision

  • Uttarakhand Judicial Services

    Subject revision

Related exam syllabi

More solved explanations in Discharge, impossibility & frustration