A contractor takes an advance under a valid government construction contract, then abandons the work without justification. The Government rightfully rescinds the contract. What can the Government…

Question and options

A contractor takes an advance under a valid government construction contract, then abandons the work without justification. The Government rightfully rescinds the contract. What can the Government claim?

  1. The advance, but no damages, since a party who rescinds loses them

  2. Punitive damages for the deliberate abandonment of the work

  3. No claim, since rescission puts an end to the contract and its remedies

  4. Compensation for the loss caused by the breach, despite the rescission

Answer and explanation

Correct answer: D - Compensation for the loss caused by the breach, despite the rescission

Section 75 of the Indian Contract Act, 1872 entitles a person who rightfully rescinds a contract to compensation for any damage sustained through its non-fulfilment, assessed under section 73 for loss arising naturally from the breach. Rescission therefore does not bar damages, and Indian contract law awards compensation for loss, not punitive damages.

Practice for these exams

  • All India Bar Examination (AIBE)

    Subject revision

  • IIT Kharagpur LL.M. Entrance

    Subject revision

  • UGC NET Law

    Subject revision

  • CLAT PG

    Subject revision for a passage-based exam

  • CUET PG Law (LL.M.)

    Subject revision

  • AILET PG

    Subject revision

  • Supreme Court Law Clerk and Research Associate

    Subject revision

  • Bihar Judicial Services

    Subject revision

  • Uttarakhand Judicial Services

    Subject revision

Related exam syllabi

More solved explanations in Remedies for breach & damages