What limitation period does Article 54 of the Schedule to the Limitation Act, 1963 prescribe for a suit for specific performance of a contract?
Question and options
What limitation period does Article 54 of the Schedule to the Limitation Act, 1963 prescribe for a suit for specific performance of a contract?
One year
Two years
Three years
Twelve years
Answer and explanation
Correct answer: C - Three years
While substantive remedies for specific performance of contracts are governed by the Specific Relief Act, 1963, the period of limitation for instituting a suit for specific performance of a contract is prescribed by Article 54 of the Schedule to the Limitation Act, 1963 as three (3) years—computed from the date fixed for the performance, or, if no such date is fixed, when the plaintiff has notice that performance is refused.
Practice for these exams
-
Chhattisgarh Judicial Services
-
CUET PG Law (LL.M.)
Subject revision
Related question papers
Related exam syllabi
More solved explanations in The Schedule - periods for suits, appeals & applications
- For bringing on record legal representatives of the deceased party, application is to be made within
- Where are the ordinary criminal-appeal and revision limitation provisions in Schedule Articles 114, 115 and 131 found, distinct from the BNSS chapter limiting…
- Under the Limitation Act, 1963, what is the limitation period for a suit for which no specific period is otherwise provided?
- What limitation period does the Schedule to the Limitation Act, 1963 prescribe for a suit on a dishonoured foreign bill where protest has been made and notice has…
- What limitation period does Article 124 of the Schedule to the Limitation Act, 1963 prescribe for review of a judgment by a court other than the Supreme Court?